Grid Connection Feasibility Study
for Developers and Investors

Pursuing an unviable site may only cost £thousands in wasted site acquisition resource, but the opportunity cost – backing a winner elsewhere – will be £millions

ENERGY STORAGE

Where Roadnight Taylor can help

By avoiding unviable sites you’ll:

  • Save on in-house and external site finder costs

  • Save on failed connection application fees

  • Save on legal and professional fees

  • Free up cash and resource to focus on viable sites

By focusing on viable sites you’ll:

  • Accept more connection offers

  • Enter into more option agreements

  • Achieve planning consent on more sites

  • Reach financial close on more schemes

The difference in numbers:

  • More than 2.5GW of viable connection offers per annum

  • >80% of connection offers accepted

  • Hundreds of wasted applications avoided

  • Five times the application success rate of the market

The technical, commercial or regulatory key that will unlock the grid at transmission or distribution level – and so the potential in a site – is often obscured from all but those with the very deepest of expertise.  Finding it can be worth £millions.

The technical, commercial or regulatory key that will unlock  the grid – and so the potential in a site – is often obscured from all but those with the very deepest of expertise.  Finding it can be worth £millions.

The challenge

  • Nationally, about 15% of HV and EHV generation connection offers are accepted by developers, in part because:

  • Many applications are submitted on the wrong part of the network because:

    • developers rely on network operators’ heat maps; and
    • developers rely on budget estimates; but
    • heat maps and budget estimates give as many false positives as they do false negatives
  • As frequently, the wrong application is submitted on the right part of the network

  • DNO System Planners have neither the time nor the authority to find and advise you of a connection solution – pre application – in spite of most having the inclination

  • It stands to reason that System Planners would not all have the combination of technical, commercial and regulatory expertise and experience – and the tenacity – to consistently identify a technically feasible and cost-viable connection

The solution

Working at both transmission and distribution levels, we carry out a thorough, skilled, detailed and efficient study of publicly-available network data in order to rapidly deduce whether a technically-feasible and commercially-viable connection can be achieved – and, as appropriate, liaise with the relevant network operator’s System Planner to augment our study and gain additional network intelligence.

Short of carrying out a feasibility study for many £thousands – and in a timeframe that works for few serious developers  – DNO and TO System Planners are unable to do this work.  Few developers, if any, have the necessary in-house capability to deliver the requisite results.

Our feasibility studies are trusted and valued by a rollcall of the UK’s leading energy scheme developers – the smart money. Some leading developers have built substantial pipelines via our feasibility service.

Jake Dunn

“Roadnight Taylor’s specialist engineers have carried out a number of feasibility studies for Vattenfall’s schemes, giving us an incredibly high success-rate.

Significantly, for me, is their ability to take our vision and commercial creativity, and deliver viable, sophisticated connection solutions for complex, multi-technology colocation projects (wind, solar, storage and hydrogen electrolysis). They are extraordinary.”

Jake Dunn, leading UK expert in co-location 
Commercial Development Manager, Vattenfall Wind Power

Who does the work?

Our extraordinary team of Connectologists® have the hands-on technical, commercial and regulatory experience of the highest order – having held responsibility for many thousands of EHV offers and applications.  They are tenacious, diligent, self-assured and professional – and they are on your side.

Some of our current developer feasibility study projects

  • Gate 2 submissions - a practical guide

Join us for a webinar designed to bring clarity to the Gate 2 submission process for energy project developers and stakeholders. This session will help you understand what’s ahead and how to approach the Gate 2 evidence window with confidence.

  • Top 10 grid connection tips

Getting your project connected to the grid is no easy feat—but what are the most essential tips to maximise success? In our latest podcast, our Connectologists® battle it out to decide the ultimate Top 10 Grid Connection Tips.

  • Grid code change GC0117 podcast

Join our Connectologist as they debate GC0117 the Grid Code change proposal, initially raised back in June 2018, aimed at improving transparency and consistency of access arrangements for generation and storage connections.

  • Podcast: NGED connections team

Join Pete Aston and Nikki Pillinger and special guests Amanda Le Brocq (Director of Connections), Sarah Jeffery and Mark Baker (Heads of Strategic Customer Engagement) from National Grid Electricity Distribution (NGED)

  • Webinar: Last chance to secure your demand grid connection

Data centre, hydrogen electrolyser or industry looking to decarbonise? With the National Energy System Operator set to pause applications for demand connections at transmission, is March your last chance to secure a grid connection offer in 2025?

  • Webinar: Last chance to secure your demand grid connection

Webinar Watch: Critical insights ahead of NESO's 21 March 2025 application deadline for transmission demand connections