Penny wise, millions foolish – a lesson in the cost of not using expert advisors in energy scheme developments

2020-11-19T15:33:54+00:00February 6th, 2020|Developer Services, Energy Developers, Grid Consultancy, News|

A solar developer achieved a grid connection offer for a solar farm site but missed a crucial stage in the process and so failed to secure and safeguard the grid rights - thus losing out on any opportunity. What should they have done?

Our 2019 results

2020-03-27T12:24:20+00:00February 3rd, 2020|Commercial & Industrial, Developer Services, Energy Developers, Farms & Estates, Feasibility Studies, Grid Consultancy, News, Public Sector|

In 2019 we secured grid capacity for over 1GW of solar, storage, gensets and energy from waste (EfW) schemes, on over 3,000 acres with a lifetime ground rent of £100m. Why not join us in 2020?

Grid expertise secures a successful outcome – but it was too late for another

2020-11-19T15:34:23+00:00October 1st, 2019|Developer Services, Energy Developers, Farms & Estates, Grid Consultancy, News|

Two recent cases where our considerable level of grid expertise has been demonstrated. One case led to a lucrative outcome for a developer. The other highlighted why getting us involved at the start of a project will achieve better outcomes.

50MW gas genset and 25MW battery storage scheme in Nottinghamshire

2020-02-26T16:30:19+00:00March 16th, 2018|Farms & Estates, Grid Consultancy|

Roadnight Taylor secured 50MW export capacity for a gas genset scheme and 25MW import capacity for battery storage and reduced the connection charge by £1.5 million for a landed estate in Nottinghamshire.

40MW gas genset and 10MW battery storage scheme in Shropshire

2020-02-26T16:43:51+00:00March 10th, 2018|Commercial & Industrial, Grid Consultancy|

Roadnight Taylor secured 40MW of export capacity and 10MW of import capacity for battery storage behind the same connection for an industrial client in Shropshire.