Podcast: Risky Business

Recorded: 24 June 2026

The running time is 19 minutes.

Summary:

Since recording, we’ve confirmed that the decision to take the Taunton to Alverdiscott circuit out of service — and when it returns to normal running — sits with NESO. This is outside the control of NGET and National Grid Electricity Distribution (NGED); the summary below reflects the correct position.

Catherine Cleary is joined by Connectologists® Philip Bale and Nikki Pillinger to unpack a summer of generator constraints across Devon and Cornwall, and what it reveals about assessing network risk.

· three coincident issues (equipment refurbishment, delays in new assets being installed and transmission generation outage) have resulted in high voltages across the peninsula

· to manage this, the 400kV Taunton to Alverdiscott circuit was taken out of service, a decision controlled by the NESO

· this leaves the DNO planning around the 132kV K Line for a rare but real N-1-1 fault scenario with a risk of circuit overloads

· ANM is no guarantee to keep access, when constraints are severe enough there will be significant curtailment

· coordinated reactive power support from connected customers could help, and NESO has ruled out a distribution-level market for it, for now

· Philip’s takeaway: understand your real exposure and start that conversation early with network operators

This content was recorded on an earlier date. The connections landscape changes rapidly, so please treat any facts, figures, and guidance as a point-in-time view and verify current information before relying on it.

Transcript:

00:01:06 – 00:01:13 – Catherine Cleary

Hello, and welcome to another Roadnight Taylor podcast. I’m joined by Nikki and Phillip. So hi, guys.

00:01:13 – 00:01:14 – Philip Bale and Nikki Pillinger

Hi.

00:01:14 – 00:01:33 – Catherine Cleary

And today we are talking about risky business, so specifically generator constraints in the southwest, and a bit of an update on some stuff which has been happening this summer, and affecting quite a large number of generators, down in the Southwest of Devon and Cornwall region.

Philip, do you want to kind of give us an overview as to what it is technically that’s actually happened?

00:01:34 – 00:01:59 – Philip Bale

Yeah, so apologies for this one. It’s going to be a little bit complicated, but we’ll run through it, and we’ll just gloss over the general theme as to why it’s occurred. Southwest Peninsula, quite tricky, so we’re talking about here from Taunton all the way down from Alverdiscott, Indian Queens, and then back on the Southern coast again through South Devon; quite a difficult network to manage, has been for quite a long time, suffers with high volts and low volts because of where it’s…

00:02:00 – 00:02:01 – Catherine Cleary

Because it’s a really long…

00:02:02 – 00:02:25 – Philip Bale

It’s a very long ring all the way down there. There is usually transmission-connected generation that operates and controls the voltage for the reactive power control, a fairly major one of those is offline at the moment for refurbishment. At the same time, there is another piece of equipment in another substation which is also being replaced, along with some extra equipment which is not yet in place at the moment.

00:02:26 – 00:02:29 – Catherine Cleary

It’s a bit of a perfect storm of lots of things happening at once.

00:02:30 – 00:03:29 – Philip Bale

Three different things all happening at the same time, which then means that there are high volts across the peninsula, which has led NESO to take the decision to take out one of the circuits between Indian Queens and Taunton; and it remains at NESOs discretion as to when the network returns to normal running arrangements. And if people in the know, because of the southwest, Alverdiscott is a double tee in, which means you lose the transformer at Alverdiscott.

Also at the same time, to make it even more of a perfect storm, there was another transformer at Indian Queens that’s out of service at the moment. So in order to manage the voltage, that action has been taken on the 400kV, which then leaves the DNO in more challenges because they have what’s called the K Line, which is the 132kV line that runs between Indian Queens and Alverdiscott, and they have to plan for the next credible outage, which at the moment they’re under an N-1-1, which is another -1, which means they lose a lot of transformers, and theoretically all the power has to go through the K Line to Indian Queens causing network overloads.

00:03:29 – 00:03:33 Catherine Cleary

So, we’ve got outages that are happening at the transmission network level.

00:03:33 – 00:03:34 – Philip Bale

Yep.

00:03:34 – 00:03:49 – Catherine Cleary

Sort of as, as you described, you know that’s just kind of, I guess, bad luck, you know, that you’ve had three sort of coincident issues. So, outages at the transmission level, and then you’ve got the DNO network running in parallel with that transmission network, and they’ve taken an outage kind of proactively of that circuit. Is that what you’re saying?

00:03:50 – 00:04:04 – Philip Bale

The 400kV line has taken an outage, and then as a result of the 400kV line and losing a super grid transformer, then the DNO is being aware of what’s the next credible scenario that could happen, and what would the overloads on the network be, and how do I manage those?

00:04:04 – 00:04:15 – Catherine Cleary

Okay. So, the DNO hasn’t taken the outage; they’re just saying, “well, actually we need to make sure that we’ve kind of, I guess, sort of contracted, or managed the situation in the event that that outage happens.” That’s your final -1.

00:04:16 – 00:04:17 – Philip Bale

Yes.

00:04:17 – 00:04:21 – Catherine Cleary

So, this is sort of the transmission system and then the DNO having to plan for that minus, minus a, a further outage.

00:04:22 – 00:04:34 – Philip Bale

If it’s credible, they have to make sure it’s happened. If they don’t, the risk of cascade, which is why it puts them in such an awkward situation here, is that they have to make sure that there are not overloads and cascades, and the whole of the southwest gets turned off.

00:04:35 – 00:04:42 – Catherine Cleary

00:05:12 – 00:05:26 – Nikki Pillinger

Including, and this is in, in kind of national news so, you know, we can say this, are the country’s largest community renewable generator has been impacted by this as well. So yeah, really quite, quite detrimental impact on them.

00:05:27 – 00:05:40 – Philip Bale

And obviously just from people that hear that own these projects will fully understand when a project recent or connects fairly recently, at that point they have the biggest amount of debt, they have the biggest interest payments, and at that point being turned off at that point is the most critical.

00:05:41 – 00:05:59 – Catherine Cleary

Yeah, absolutely. So, I guess, I mean some people might say, “well, why, why does DNO ever have to turn a generator off in that scenario? Haven’t we got things like ANM which would sort of like more proactively manage that risk or inter-trips in the event that, you know, generator only goes off if that’s, that N-1 scenario, that extra N – 1 scenario actually occurs?”

00:06:00 – 00:06:50 – Philip Bale

I mean, I think that’s a good point in terms of because of this scenario at the moment, I mean, we do these types of analysis for customers anyway, and we’ve looked at this network fairly recently. We would plan for an N-1 -1, so a transformer being out of service, for instance, for a maintenance followed by another fault – I don’t think most engineers would look at a scenario which is an N-1-1 for the next credible fault of going through. It’s a pretty rare event to come through.

ANM schemes are being refreshed and being updated, which is another element of coincidence that’s happening at the same time, which then means that that’s not an option for going through. But even if it was there, losing two transformers and the risk of a third going off means that the pre-event limits would probably be very heavily constraining them during that time anyway.

00:06:51 – 00:06:58 – Catherine Cleary

Yeah. So technically yeah which we’ve seen before, isn’t it? ANM is not a silver bullet, you know? If you get bad enough set of constraints on the network, then everyone ends up going to zero anyway.

00:07:10 – 00:07:24 – Philip Bale

00:07:24 – 00:07:36 – [BREAK FOR MIDDLE SECTION]

Yeah, and I think all of these customers have accepted the fact that they are non-firm connections with ANM. The key thing is how well do any customers fully understand the risk to their networks and how can they control the risk? And I think the answer is that they can’t, because as we’ve explained earlier, all of these different things, some of which are transmission level, some of which are distribution level, some of which is just very bad luck, are completely out of their control.

00:07:37 – 00:08:27 – Catherine Cleary

Yeah. And I guess, like picking up on that kind of point, I don’t think, I think the purpose of this podcast today really is kind of, like, to discuss this topic and what it might mean for, for sort of designs in future rather than, you know, it doesn’t sound like it’s anyone’s individual fault, you know?

Like there hasn’t been any kind of poor practice or anything like that, so I suppose, you know, if this happens, if these were domestic customers or something being turned off, or perhaps if this has happening at the transmission level and transmission customers were being turned off, we’d probably see quite a lot about that in the sense of it either being reported through a network operator’s kind of regulatory requirements to report to Ofgem, things like customer interruptions or NESO’s kind of much more sort of public reporting on, on how they balance the system, under outage conditions.

This sounds like it’s sort of slightly in between those two scenarios. So, is there a risk that actually there are lots of people who won’t be aware of this happening?

00:08:28 – 00:09:36 – Philip Bale

Yeah, I think there’s a lot of people who won’t be aware. I think obviously the reason why it’s in the public domain is because there was an article in the national news where it was discussed.

But yeah, if you weren’t any of those specific customers in terms of being constrained, probably wouldn’t have become public knowledge unless one of them had gone to the papers. I think in the future there is a lot of conversation around, and as you said, at the moment, there is no central reporting, carrot stick approach around turning customers off at ANM. In the future, some of the DNOs are saying is ED3, we think this should be reported, and we think there should be either rewards or penalties on the back of this, which then potentially will result in people looking at networks in a slightly different way of trying to minimize the impact on customers.

How that works in practice, incredibly difficult, some of which is very difficult to unpick because it’s historical things like the fact, that Alverdiscott is a double tee network at the moment and will probably remain a double tee network for a, a reasonable amount of time until there’s other works needed that puts in a proper 400kV board; some of them become very difficult to unpick

00:09:37 – 00:10:13 – Catherine Cleary

I guess that, that reporting is sounds like a really good first step because I think at the bare minimum it would help transparency. So, if networks were reporting regularly on, you know, disconnecting non-firm generators, because that’s what we’re talking about here, you know, these generators, they don’t, it’s not that they have a contractual right to remain connected to the system, you know, DNO’s entirely entitled to disconnect them. But I guess a bit more kind of transparency on the reporting of how often that happens, and you know, perhaps a bit more investigation when there are really big events like this which have a really significant impact. That feels like that’d be really helpful to the developer community as well because, it might sort of start to sort of spread awareness of that risk and maybe let some lessons be learnt in the future.

00:10:14 – 00:11:22 – Philip Bale

I think some DNOs are actually reporting this already, but I don’t think it’s routine across all of the DNOs that have ANM schemes.

And I think, like you said, it’s understanding the big lessons learnt from this. I mean, this is a pretty big one. The outages we’re talking now I think is around the end of September, and they’re already off, which is around the peak sunniest periods of the year. And I think for me and I think for all of us where we have these conversations, it’s around what are the specific learning that’s come from this, and then how does it apply more generally across other network areas? How can more be done to look more proactively at the levels of risk? And ultimately, it’s going to get harder and harder the more complicated networks get, the more they’re pushed to the limits, the more we’re trying to replace transmission assets. I mean, we all know at the moment we’ve got a phenomenal amount of work that needs to be done across both transmission networks and distribution networks. And during that period of significant rebuild, how much risk is taken? How do you manage that? How can you put control systems in place to manage it? And what level of fairness of risk is then apportioned out to people?

00:11:22 – 00:11:30 – Catherine Cleary

Do you think that there’s anything, so it sounds like at the moment, you know, those affected generators, unfortunately, in fact, there is nothing they can do really, this, this outage is going to need to, to take its course?

00:11:31 – 00:12:29 – Philip Bale

I think there’s potentially things that could be done. So, I think this is something that at the moment, the reason for taking the 400kV outage out is a lack of reactive power control.

I actually think that there’s potentially an opportunity if there’s enough relevant customers who have the opportunity to offer some reactive power control, potentially enough to keep the 400kV line in to mitigate that, possibly then operating way in excess of the G99 requirements, possibly them operating at a very extreme fixed power factor for a longer period of time. There’s a common saying that vars don’t flow, don’t travel very well, that they will be absorbed by the network. So there does need to be the study of which customers, how much coordinated, how many customers, which customers would give the better response? How much does that derate the network? So, a customer in the middle of the K-line, the reactive power would be absorbed by the network, and sort of what are the impacts?

00:12:30 – 00:12:42 – Catherine Cleary

But if you’ve got customers, you know, who are inverter connected, and they’ve got that capability to offer quite significant VAR contributions sometimes, and perhaps they’re already connected at 132kV busbars, you know, they would be potentially ideal candidates.

00:12:43 – 00:12:56 – Philip Bale

And I think at the moment it’s tricky because the network operators find themselves in a fairly difficult situation having to, to do these actions. Very difficult to try and test something live at a very difficult time. But I think this is the sort of thing…

00:12:56 – 00:12:59 – Catherine Cleary

On the other hand, it can’t get worse than off, so maybe it’s the ideal time to test it.

00:13:00 – 00:13:03 – Philip Bale

Yes. I think the worry is the, what happens if scenario, which that means everyone’s off.

00:13:03 – 00:13:04- Catherine Cleary

Yes, that’s true.

00:13:04 – 00:13:30 – Philip Bale

As opposed to, and then it does get reported, and there are penalties that come with it. But I think it’s more a case of who needs to have that flexibility in their back pocket, and then is there a payment for it or not? And those sorts of things and when should someone ask for it, and is it in the generator’s interest, and when is it not in the generator’s interest, and should it be a DSO service? And I know this is a very relevant aspect at the moment.

00:13:31 – 00:15:10 – Catherine Cleary

Yeah. Well, it’s very timely. I mean, so NESO had been looking at specifically reactive power, how it’s procured, and whether or not embedded generators should be able to kind of participate in that market and provide reactive power.

So, at the moment, I mean, as sort of really exemplified by what’s happened in the southwest, it is really only transmission connected parties, so directly connected transmission generators, that provide these commercial reactive power services to get paid by NESO providing that as a service.

Interestingly, of the options that were sort of looked at, and this only came out last week really, but, of the options that were looked at, which was, you know, NESO could extend that down to distribution customers; so they would still be doing the procuring, but they would consider taking, you know, for example, that 132kV large customer on the DNO’s kind of bars at a GSP; they might consider, you know, a reactive power provision from them. They could ask, the DSOs to kind of, you know, have a similar reactive power market, but at distribution level; they could, you know, DNOs could act as a sort of aggregator, so they could kind of like aggregate up, you know, appropriate volume; or we could say, no, there’s no market mechanism, you know, a DNO should effectively just sort of mandate the minimum requirements from a generator. And interestingly, as of last week, NESO had come out kind of fairly firmly saying, we’re going for number four – you know, we’re not going to create a market, we’re just going to sort of you know, keep it simple, but it sounds like, I think this is a kind of possible case where doing that maybe creates the wrong incentives, you know? So, you’ve got these complicated scenarios, you’ve got network outages on a transmission network. They have an impact at distribution network, and your overall system operator doesn’t actually have the tools to incentivize a distribution generator to act in a certain way.

00:15:11 – 00:15:28 – Philip Bale

Yeah. And as a result, it’s then impacting other customers and I think Nikki, sort of as you deal a lot with customers at actually the later stage, I think most of those customers, if they know that there is a requirement for it that would build in, if it keeps them on, they would do it without being paid.

00:15:28 – 00:15:29 – Nikki Pillinger

Yeah, totally.

00:15:29 – 00:15:53 – Philip Bale

The question is, is that a moral aspect of it? Because if you’re paying for someone that’s connected at transmission, and secondly, is it just the right thing to do? So, is there, is there an element that actually the DSO could manage those, they could do things, and what’s your view around customers wanting to participate in those ancillary service type things, new services that could be offered at sort of DNO level?

00:15:54 – 00:16:22 – Nikki Pillinger

So, I think customers are always obviously looking for different revenue streams. I think that’s a really positive thing. I think, you know, that’s why we have the DSOs in the first place, so that customers can actually kind of engage with their, with the network in a bit of a different and more kind of flexible and agile way.

And I absolutely think that the DSOs should have that kind of mandate from, from NESO to actually do that and to create those markets and to create those incentives, and I think customers would, would be up for that.

00:16:23 – 00:16:58 – Philip Bale

I tell you what, it’d be really interesting if we have a poll from the people that are connected, mainly probably the 132 or 33kV customers that are connected, who would be interested in doing those reactive power models, what could their plant actually do for that network? Thinking about it, because it’s inductive and absorbing VARs, actually it will end up growing as you pull more VARs through a transformer. It ends up increasing the magnitude of what’s coming through. It’d be really interesting to see if we get an excess of 50 MVAR, 100 MVAR, where the limit actually then becomes the SGTs; then with possible Super Grid Transformers, tap staggers, circulating current going through.

00:16:59 – 00:17:00 – Catherine Cleary

Could make a real impact.

00:17:00 – 00:17:09 – Philip Bale

You could find a scenario where you have an excess of 50 or 100 MVAR in that Southwest Peninsula, which actually then means that you don’t need to build new plant and have that flexible capability.

00:17:10 – 00:17:34 – Catherine Cleary

Amazing. Right, so answers on a postcard or possibly in the comment section of LinkedIn or wherever we post our podcasts. Yeah, we don’t need a NESO RFQ, we just need to find out, you know, are the generators in the Southwest interested. I mean, I think we’ll, we’ll leave it there perhaps, because it’s quite as you said, Philip, it’s quite a technical subject, but a really interesting kind of timely point to report on. Maybe we’ll come back to this in our Grid News and Views if there are further developments.

00:17:35 – 00:18:52 – Philip Bale

Agreed. And I think just one last takeaway from this is that obviously whenever connecting to any network, especially the bigger the customer you are, the more you have to be aware of the risks. I would say, and I think we’d probably all agree, that the Southwest Peninsula is a very tricky network, interconnected GSPs, multiple split options around there, very long circuits, more complex than most; I think there is a requirement for customers to be better aware around what their levels of risks are, most people only look for normal network running., some people look for N-1, do customers need to be looking for N-1, N-2; understanding the frequencies, engaging with the network operators, transmission distribution to understand the frequencies and the events and the worst case, the best case, and, and start that conversation around what could happen. If it happens, how long? What are you doing to try and minimize this risk? If we’re at N-1, what actions are being taken to try and make sure we don’t get to N-2? I think more and more people are going to start talking about those and possibly ensuring against them in the future. So, I think if you are a developer and you’ve got these big projects, how aware are you of the risks? What are you doing to actively try and understand them? Obviously, we don’t want people to be scared but just informed.

00:18:53 – 00:18:55 – Catherine Cleary

Yeah, yeah. And I suppose that reporting piece will, will help.

00:18:55 – 00:18:56 – Philip Bale

Indeed.

00:18:57 – 00:19:06 – Catherine Cleary

Fantastic, amazing. Well, thank you for sharing that, the geeky knowledge, Philip. Thank you. And, and also very much, like, I think that customer impact piece, Nikki, is incredibly important. Thanks very much, guys.

00:19:07 – 00:19:07 – Philip Bale

Thanks, both.