Podcast: Ofgem’s Transforming Connections consultation explained

Recorded: 13 October 2026

The running time is 31 minutes.

Summary:

Unreliable data and inconsistent service have long made connections harder to navigate. In this connectology® episode, Connectologists® Rachael Eynon and Alex Ikonic work through Ofgem’s two latest consultations, sharing what is proposed and where questions remain:

  • better data: Ofgem’s Transforming Connections Data (TCD) consultation proposes a new Demand Capacity Register, a demand works register and improvements to existing registers
  • a clearer customer journey: Ofgem’s Transforming the Connections Experience (TCE) consultation proposes service level agreements (SLAs), a named point of contact and minimum offer content
  • stronger recourse: TCE also proposes higher Guaranteed Standard of Performance (GSOP) payouts and a move away from zero-value liquidated damages, with detail still to come
  • timing for implementation: Ofgem is considering whether the TCE changes should start in summer 2027 or April 2028
  • time to respond: the TCD and TCE consultations both close on 06 November 2026

Alex mentions a client who found the project status on the TEC register was wrong more than 50% of the time in the sample they reviewed. Since recording, the NESO corrected this within days of the client raising it. That kind of responsiveness deserves recognition.

Transcript:

00:01:29 – 00:01:37 – Rachael Eynon

Hello, and welcome to another connectology® podcast from Roadnight Taylor. I’m Rachael Eynon, and today I’m joined by Alex.

00:01:38 – 00:01:39 – Alex Ikonic

Hi, Rachael.

00:01:40 – 00:02:32 – Rachael Eynon

And yeah, just the two of us today, and we thought we’d do a bit of a deep dive into Ofgem’s two consultations that they’ve published recently that’s the TCD, Transforming Connections Data, and TCE, Transforming the Connections Experience. So, Alex and I have been deep in the 174 pages, across those two consultations. So, we can try and give you a bit of an update, and then if we’ve got some time at the end, we’ll cover some of the other consultations and other updates that we’ve had across the industry over the past few weeks.

So, Alex, hoping you can give us a bit of a background on how we got to the point of these two consultations being published. So, I think it started all the way back in 2023, is that right?

00:02:33 – 00:04:15 – Alex Ikonic

Yeah, I think that sounds about right. It’s definitely been ticking along for a while, so at the time, I think it was part of the connection action plan, so Ofgem decided to undertake, like, an end-to-end review, so it was a very sort of wide-ranging review of kind of all things connections, kind of starting from the, like, very early-stage pre-connection feasibility, like, all the way through the customer experience.

So, the first consultation was in November of 2024, so almost two years ago now. I think that set out seven key themes, so there were quite a few of them. So, the first one was connections data, then we were thinking about standards of service timeliness and kind of meeting connection dates, and quality of offers as well and, how ambitious the connection dates offered were.

Then there was a separate topic about smaller connections and about disputes and determinations. And so, it was a sort of very, very wide-ranging review, and I think when it first came out, we were all very excited to see it. I think it was a very, like, positive step definitely in the right direction.

Since then, there was a bit more, you know, detail published on all of those themes and kind of initial thinking that Ofgem had kind of following those consultations. And we spent a lot, a lot of 2026 kind of going through workshops, like, in the industry and so, we’ve been particularly involved in the connections data one, but I think we’re aware that there have been some other ones as well, kind of covering various different topics, and kind of delving into the detail of, of all of that a bit more.

And that’s kind of led us to today, where we have these, like you said, very long consultations, that cover kind of all, all of these themes and kind of proposals for them as well.

00:04:16 – 00:04:35 – Rachael Eynon

Great. Yeah, so we’ve been on quite a, a long journey with this, and I think over that time the, the themes have sort of developed as well.

So, now that we’ve got these two consultations, the TCD and the TCE, that’s kind of a split out of those seven themes. Is that right? So TCD is dealing just with theme one.

00:04:35 – 00:04:36 – Alex Ikonic

Yes.

00:04:36 – 00:04:53 – Rachael Eynon

On connections data, and then TCE kind of wraps up everything else, about that kind of customer intent journey. And then we’ve got the smaller connections point that Ofgem have taken out and kind of set aside for later.

So probably more to come on that.

00:04:54 – 00:04:55 – Alex Ikonic

Yep. Yeah, exactly.

00:04:55 – 00:05:11 – Rachael Eynon

Great. So, we’ve kind of split this up amongst ourselves as well to do our research. So, you’ve been looking into TCD, and I’ve been looking into TCE. So, I guess can you give us an overview of what TCD, what’s the problem that TCD is trying to solve?

00:05:12 – 00:06:01 – Alex Ikonic

Yeah, so, connections data has, you know, as many people in the industry will be aware, it’s been quite a bit of a pinch point, especially over the last couple of years. So, there’s a very big focus on kind of data quality and accuracy of the data, and kind of in particularly how to deal with errors in the data and the kind of links between different data sets and the kind of consistency of the data.

So, I think, yeah, very excited to kind of see how these develop. I think no one could argue that, that we, you know, don’t need better connections data. In fact, I was actually talking to one of our clients a little while ago, who’d been looking at the tech register, and for the sample that they were looking at, there was actually the project status for, for different projects which they said was wrong more than 50% of the time – so I think, yeah, could definitely use some improvements there.

00:06:02 – 00:06:05 – Rachael Eynon

Wow. Yeah. Definitely.

00:06:06 – 00:08:43 – Alex Ikonic

But yeah, as part of the TCD, so there’s been a few kind of things that are being proposed, so there’s, crucially two new data sets, so the demand capacity register, so as most people are aware, there’s kind of no equivalent to the embedded capacity register or the transmission entry capacity register, the tech register for demand. So that’s been a very much like a, a black box of, you know, who’s connecting where, and now Ofgem are suggesting that DNOs will publish like embedded demand connections like individually per DNO, and NESO will publish a demand capacity register to cover transmission connected demand. So, the idea is that’s going to be done monthly.

I think there’s still like a few open questions as to kind of how that’ll work, you know, what’s the threshold for inclusion. So, there’s, you know, different things that have been proposed, and there’s also a bit of a question of how are we going to treat storage there because it obviously has like an import and an export element, but I think it’s just, it’s a really good thing that we, we are seeing this progress, so, yeah, definitely on board with that.

The other key thing that’s being proposed is the demand works register, so that’s going to kind of list, you know, potential reinforcements on the distribution network, any kind of like planned reinforcements, and that’s the idea of that is actually to kind of be the new long-term development statement appendix nine, which is like the planned reinforcements bit because the LTDS will be retired quite soon, so, and this will kind of be the, the new data set for that and the idea is that this will also include kind of any works on the distribution transmission interface, which, you know, for most embedded projects will, yeah, be quite an important thing to find out. So, that’ll be good, and there’ll be like a link to the transmission registers as well, so you can kind of cross-reference what’s going on there.

And one of the other things is there’s been quite a few improvements that have been proposed to existing registers. And so that’s stuff like the Tory register, the transmission works register, and the tech register, so again, that’s definitely a good thing to see. I think it’s going to be quite a quick win, rather than if we were going to create something new. I think having good data is going to be really critical going forward. I think, you know, anyone that wants to submit a new application in the window coming up, or anyone who’s kind of seeking to optimize their existing connection and, and needs to Mod App, you know, kind of the key principle is like you need to have good data in order to make a sensible request. So, yeah, as far as I’m concerned, these can’t come quickly enough.

00:08:44 – 00:09:08 – Rachael Eynon

Definitely, sounds like the links is really important. Like, just when you’re talking through them all there, you can already see how there’s potential for overlap the more data sets and, that we have access to. I’m thinking about, yeah, storage, as you’ve said, if that could technically appear on two registers, or the more kind of hybrid projects that we have now across generation and demand and making sure that those records reference each other and are accurate is going to be even more important.

00:09:09 – 00:09:37 – Alex Ikonic

Yes. Yeah, definitely, because I think that’s something we’ve definitely seen in the kind of previous data sets that we have now. There’s a lot of inconsistency, and it’s very hard to get them to match up. So, I think having this idea of you know, like a unique identifier for a project or a technology within a project, and for different reinforcements, I think it’s going to be really good for people to be able to like cross-check between different data sources. And I think that will really kind of help improve like confidence of the data as well.

00:09:38 – 00:09:51 – Rachael Eynon

Definitely. And how does that link to the CIM proposals, the Common Information Models? Is this the, the same kind of proposal or, or are those separate things, but this is important in linking them together?

00:09:52 – 00:10:32 – Alex Ikonic

So, I think it is separate but definitely linked. So, the CIM currently covers the distribution network, so we did discuss in these work groups, and it’s also mentioned in the consultation that any kind of distribution information should be like linked with the CIM where the CIM is applicable. So, I think that definitely will be quite useful.

I think there’s probably a slightly different purpose between these datasets in that they should be machine-readable, but they also should be accessible to kind of your regular project developers and someone who doesn’t, you know, have power system software to kind of deal with the CIM as well.

So, I think there’s an interface there as well that’s going to be quite important.

00:10:33 – 00:10:51 – Rachael Eynon

Definitely, yeah. And I could see this becoming even more important or potentially more useful as we get into kind of a world of AI, where we have AI to help us kind of query these data sets and sort of understand the bigger picture at least a bit more quickly yeah, to inform new applications and things.

00:10:52 – 00:10:59 – Alex Ikonic

Yeah. And that’s why that kind of, like, machine-readable part is going to be very important as well in, in making sure that that data is something that we can actually depend on.

00:11:00 – 00:14:23 – Rachael Eynon

Yeah, great. Yeah, so I think, then, that probably brings me onto a lot of the points that have been mentioned in the TCE, so this is kind of everything else aside from the data piece.

So, addressing those pain points that, customers have at the moment in the connections process, all the way through from pre-application right through to kind of delivery of their project. So Ofgem have translated those five themes, kind of out of the seven that are in scope of the TCE, into looking at them from a more kind of outcomes-based perspective.

So, the four outcomes they’ve gotten there are having minimum requirements and kind of standards of services at those different touchpoints trying to kind of raise ambition, so having ambitious but reliable or kind of evidence-based connection dates. And then similarly timely and reliable connection dates, so kind of what can be done to address a lot of the delays that we’re seeing at the moment.

And then the last outcome is around standardizing the dispute and determinations process. So I think with this one, there have been a lot of, the kind of solutions have been outlined, and how those solutions will be delivered is kind of set out in a lot of cases. So, there’s kind of three main options that come up a lot across the consultation for these.

The kind of strongest one is that they’re delivered through prescriptive license conditions, so applying to all the network companies, and really setting out exactly how that service should be delivered, then for things that are kind of harder to quantify or might need a different approach depending on the project or the network, there’s proposals for more principles-based guidance, and license conditions.

And then the kind of more loose method of delivering them would be through just guidance itself that supports those license conditions. So, they’re the kind of three levels that Ofgem have explored to address all these pain points, and a few of those main pain points, kind of translating those into what we’ve heard from clients maybe throughout the current process.

A huge one is not having that kind of single point of contact or any point of contact, just kind of raising your queries through the portal and not hearing anything back or sending those through to dot boxes and things at the different networks, so the proposal here is to put really clear SLAs on a lot of the touch points in the process.

So, in the pre-App stage, having timelines on pre-App queries, and those would vary depending on the complexity of the queries, and then that theme kind of carries on throughout the rest of those SLAs. So, pre-application, post-application, and then post-offer queries as well being addressed within a timely manner. And then looking further into delivery, that becomes SLAs around notifying customers of within a certain timeframe about delays that they should expect to their projects. So, if we’ve got a delay from works from the TO or the DNO they’ll be required to notify the customer within a set time, which is very promising.

00:14:24 – 00:14:26 – Alex Ikonic

Yeah, I think we’ll, there’ll be a lot of developers very happy to see stuff like that, I think.

00:14:27 – 00:15:40 – Rachael Eynon

Yep. And then some are just kind of more principles around that point of contact, so making sure that everyone has a named point of contact, and that there’s some kind of continuity plans in place for, you know, as people move around teams or join and leave businesses as natural over the kind of many years that we take to develop projects.

Another one of those pain points is just around being able to understand the offer, so driven by the kind of inconsistencies in how those offers look across the different networks, and the content that may or may not be within those. So, the main proposal here is to set out exactly what should be in every offer.

So, a kind of core set of requirements, and then an enhanced core set of requirements. So that would apply to larger projects. And then there’s the kind of top tier good to have content. So framed as good to have rather than nice to have. I don’t know if that means something different, but yeah, I thought that was an interesting one because, there’s definitely some things in there that I would have expected to be considered core, but they’ve maybe ended up in that enhanced or good to have area.

00:15:41 – 00:15:43 – Alex Ikonic

And is that something that, that they’re still kind of thinking about, or is that kind of been set for now?

00:15:44 – 00:16:10 – Rachael Eynon

Yeah, so it’s been set out as the kind of initial thinking, so there’s lists against each of those. It does still seem like there’s definitely room to have further discussions on those.

Something that comes through a lot in the consultation is that there’s definitely going to have to be lots more workshops and discussions with industry to develop those guidance documents and license conditions and details. So, I think still, yeah, scope to influence those.

00:16:11 – 00:16:12 – Alex Ikonic

Good good.

00:16:12 – 00:16:24 – Break

00:16:24 – 00:17:39 – Rachael Eynon

Yeah, and another one of those pain points, are just dates being kind of so far in the way, so what can we do to make dates ambitious but still be achievable?

So, this is one of those ones that’s landed in that kind of middle principles-based category because, there are a lot of concerns that if you try and make those dates too ambitious, then they won’t actually be deliverable. But then on the flip side, there, there’s kind of a concern that network companies will just be incentivized to give people later dates so that they’ve got that flexibility built in.

So I think that’s one that’s still needs a lot of work to kind of look at what exactly those principles would be, and another one that came out of that was, making sure that people have the opportunity to opt in for earlier connections, so that’s one I thought was really interesting, just in terms of how that interacts both with kind of existing, sort of earlier access arrangements that we have, but also with the future capacity reallocation process that we’re going to need through, yeah, the after Gate 2 to whole queue when we potentially have terminations and sort of gaps to fill in the queue.

So, yeah, that one is again one that they’re looking for a lot of input on.

00:17:40 – 00:17:44 – Alex Ikonic

Yeah, I mean, it sounds like it’s, they’ve gone into a lot of detail there, so I think that there’s a lot to feedback on.

00:17:45 – 00:18:37 – Rachael Eynon

Yeah, definitely, and then last couple, so a lack of progress updates, I think, is a big one. So that comes back to those SLAs, and making sure that network companies are communicating delays, and then there’s also a proposal for a change control process, so kind of change logs and making it really clear what has and hasn’t changed between different variations of offers and when there’s kind of changes to program.

So, I think that’s underpinned by a shared delivery program that the network companies would need to have with the customer. So yeah, think that’s a really promising one as well, and there was mention of outage planning as well, which I think we’re seeing becoming a more prominent topic in discussions.

So, making sure that that plan is clear and that customers have enough information to understand, dependencies so what could change that and what the impact would be if the network companies was delayed or if the customer was delayed.

00:18:38 – 00:18:59 – Alex Ikonic

Yeah, I think and then I think a, a lot of those things that kind of are later on in the project, like outage planning and any kind of, like, delivery, sorry, delay notifications, I think that’s going to be really important going forward because it, we’ll see so many projects kind of come up against, you know, lots of problems like that. So yeah, very promising to see those steps.

00:19:00 – 00:20:16 – Rachael Eynon

Yeah. That’s a good point, I think particularly if we’re kind of moving into a space where we’ve, we’ve just got lots of people through the offer process, and, you know, potentially, at least in that next window, we won’t be seeing quite as many new applications, it’s sort of making sure that we get the downstream process right from post-offer.

And then the last one, so if we do still see those delays, what’s the kind of routes for recourse on that? So, this looks at strengthening GSOPs so Guaranteed Standard of Performance, which applies at distribution, and increasing some of the payout values that already exist there.

And then from the transmission side, it’s moving away from a zero value of liquidated damages, which is as it has always been in offers just a kind of, “this will be zero.” So, yeah looking to increase that, but this is one of the kind of least developed areas in the consultation, so think we can expect potentially an RFI in that area. But, definitely some more information from stakeholders on what good would look like and what those figures should be in the kind of current market to I guess, make them bite a bit.

00:20:17 – 00:20:24 – Alex Ikonic

Yeah, that all sounds really good, and but yeah, still sounds like there’s a lot of work to do.

So, was there anything in that that surprised you when you were kind of reading through?

00:20:25 – 00:21:21 – Rachael Eynon

Yeah, so yeah, I think as I said, that opting into acceleration, I think it definitely still isn’t clear how that sits alongside capacity reallocation. So, it’s kind of meant to cover post-offer, you know, you’ve got your date, and then what can be done, beyond that to kind of bring it forward.So yeah, I think there’s going to need to be a lot of work to, to set that out, and distinguish it from capacity reallocation and existing kind of non-firm access solutions as well.

And another interesting note that popped up in there somewhere was that there was a question at the start around whether IDNOs were in scope of the consultation, and Ofgem kind of said that it wasn’t particularly aimed at IDNOs, but that they are also planning a separate review of the IDNO regime. So, another call for input, I think, that we can expect in the next few months on that.

00:21:22 – 00:21:24 – Alex Ikonic

More consultations coming.

00:21:25 – 00:21:30 – Rachael Eynon

Yeah. What about you? Any, any surprises in there, or were you pretty clued up from your previous involvement?

00:21:31 – 00:22:11 – Alex Ikonic

I think not that many surprises. I think, yeah, maybe one thing I would just flag is, like, that we, we do recognize this is very much, like, a first step. So, I think, you know, a lot of changes have been proposed, and I think a lot of them sound really great, but you know, just worth noting that some of them will be done through, like, license conditions, which again, need a bit of time to develop. But others will need kind of, you know, DUCSA Mods or Code Mods. So, there’s still going to be, like, a lot of work going forward across the industry and, you know, definitely by network companies to kind of figure out the detail of them. So, I think, yes, it’s, it’s that kind of balancing the timeline and, and making sure that we, we do manage to do this in a, in a timely manner.

00:22:12 – 00:23:06 – Rachael Eynon

Yeah, that’s interesting, and I think brings us on to kind of what the timelines are for the next steps. So, I know in the TCE consultation there’s lots of mentions of follow-on work groups, but Ofgem have also said that kind of from now they will be starting to draft those license changes and guidance.

And one interesting question they’ve sort of asked is whether stakeholders think that those should be introduced in summer next year, so kind of as soon as that statutory consultation is done, or whether that should be, kind of delayed until April 2028 so that it aligns with ED3. So, I think it’s going to be really tricky there to get the balance of, like, urgency versus doing this right and kind of acknowledging the sort of steep curve that some network companies are going to have to take to get to those standards.

00:23:07 – 00:23:15 – Alex Ikonic

Yeah. I mean, I think it’ll have quite a lot of changes for some network companies. I think it’ll, yeah, be a bigger, big ask to get everyone up to speed, so.

00:23:16 – 00:24:22 – Rachael Eynon

Yeah. I think what I’d like to see as well is, a bit more clarity on, like, what might be the reward for network companies that do are in a position to adopt this quickly and kind of early ahead of time.

So, I think my gut feel would be that we probably don’t want to bring in the license obligations too quickly, for risk of kind of those not getting met and potentially, I guess, detracting from, the current issue of getting all the Gate 2 offers out and kind of tying up Gate 2 to whole queue and so on.

So yeah, getting that balance right, but allowing for those network companies that are in a better position to kind of start building towards those requirements to, do that early and kind of be rewarded for that in some way ideally.

Yeah, so I think looking at the rest of this year, it’s, for TCE, it’s starting to draft out some of those license changes and guidance, putting together those targeted working groups on the kind of specific outcomes that have been mentioned and then looking into 2027 what are the next steps for TCD?

00:24:23 – 00:24:44 – Alex Ikonic

Good question. So, I think we are going to have an outcome published from the consultation sometime in spring, and I guess depending on, you know, what that says, we’ll probably know a bit more about how all the different things will be kind of moved forward.

So, whether that is through, you know, a license change or, something that needs a Code Mod or something. So I think we will have more detail in spring on that one.

00:24:45 – 00:25:57 – Rachael Eynon

Great, yeah, and then I think through 2027 they probably both follow quite a similar pattern then, so I think next step for TCE in 27 is that consultation on the draft license changes, and then finalizing the guidance documents, so the aim is to do those by early 2027, which would allow for that potential early implementation in summer 27.

And then in parallel, we’ve also got Ofgem agreeing to do a review of the determination guidance, so that feeds back to the GSOPs and liquidated damages and kind of understanding what those routes are across different organizations. So, they’ve started a bit of this review and kind of interviewed it sounds like, the network companies to understand their current processes, unsurprisingly these differ quite a lot, so I think they’re, trying to kind of establish that baseline. But that’s definitely a piece of work that, is a bit further behind and kind of maybe won’t run to those early 27 timescales.

And then, yeah, moving into 2028, what do you think good would look like for TCD?

00:25:58 – 00:26:06 – Alex Ikonic

It’s a good question. I think, I would I, I think I’m hopeful that we will have the DCR published. I think there’s definitely, you know, the improvements to the existing data sets, I would hope that we do have those in place by then.

Again, they’re sort of, you know, existing tools, it’s just, you know, making certain improvements to them. So definitely hoping for like a quicker win with those. So yeah, I think, I hope we’ll be in a good position by then, and we’ll have all the data we need.

00:26:07 – 00:26:43 – Rachael Eynon

Great, yeah. Which would definitely, sorry, would definitely come at a really good time, thinking about kind of SSEP and future requirements for the network and applications, hopefully that can be underpinned by, by all that data as well.

00:26:44 – 00:26:47 – Alex Ikonic

Yes, and what does it look like for TCE in 2028, do you think?

00:26:48 – 00:27:24 – Rachael Eynon

I guess it’s getting everything done to that April 2028 deadline, guess could think of that as their backstop for delivery on this. So having all the guidance in place, and license conditions kind of live, and that is also the target for the kind of enhanced figures for GSOPs and liquidated damages. So, I think, yeah, April 2028 is having everything all set and the kind of full process piece, brought together.

Great, anything else then on, on TCD or TCE?

00:27:25 – 00:27:45 – Alex Ikonic

Yeah, I think just to mention again the, both consultations are open until the 6th of November, and, I think we definitely encourage everyone to respond. I think there’s some really good ideas in there, but like you said, you know, still some room for movement, on some of the details. So, I think yeah, as much kind of industry engagement as we can get for them I think we’ll be in a much better place.

00:27:46 – 00:28:00 – Rachael Eynon

Yeah, definitely. And then following on from that, getting involved in those working groups that we’re expecting to see over the next year or so to really iron out the details, and make sure we’ve got the right things in the license versus guidance and get that balance right.

00:28:01 – 00:28:02 – Alex Ikonic

Yep, exactly.

00:28:02 – 00:28:17 – Rachael Eynon

Great.

So, then I guess to wrap up, a bit of a look at what else has been happening. I think this is mainly still consultation focused, so I know we’ve had CMP 470 updates recently.

00:28:18 – 00:29:12 – Alex Ikonic

Yes, yeah, I mean, as always, it’s a busy time in the industry as there’s a lot of things going on in the background.

And so yeah, CMP 470, which is the oversubscribe technology commitment fee, so the Ofgem minded to consultation just finished, I think last week. So I think for anyone who missed that one, Ofgem’s, minded-to position is to approve the original, so I think overall we’re not sort of fully on board with that; we don’t think now is quite the right time, we think there’s maybe still a bit of you know, a few missing pieces of the puzzle and we think it would make more sense to kind of wait until the Gate 2 to whole queue exercise is complete and kind of, you know, redo the impact assessment and revisit it there. But yeah, it- it does look like that one is moving ahead – so, that’s the latest one on that one. And I think we are expecting a decision in November early or mid-November I think it was. So, yeah, watch this space.

00:29:13 – 00:29:27 – Rachael Eynon

Yeah. I guess, yeah, if we’re going to go ahead with that, it would need to be kind of timed well with the opening of the next window and having clarity on it ahead of that as well.

00:29:27 – 00:29:28 – Alex Ikonic

Great.

00:29:29 – 00:29:38 – Rachael Eynon

And then another consultation from Ofgem that we’ve seen in the past week or so was around user self-build.

00:29:39 – 00:30:12 – Alex Ikonic

Yes. So that’s another one that’s out now, I think that’s due the 13 of November. So, that’s kind of spun out of the work that’s being done on Demand Reform. But again, it could impact kind of generation and storage too. So, definitely kind of a wide-ranging one; so that’s looking at extending and kind of improving contestability, on transmission assets. So, looking at where developers can build out those assets, you know, potentially cheaper or quicker, and then they would get transferred back to the TO. So yeah, we’ll have to look at that one as well.

00:30:13 – 00:30:21 – Rachael Eynon

Yeah, and do we see that as potentially paving the way for ITOs in the future? Cause that’s to be another hot topic at the moment.

00:30:22 – 00:30:40 – Alex Ikonic

Yeah, I think it definitely could. I guess in theory, you know, it could get transferred to an ITO rather than a TO, but I think it’s, yeah, it’ll be important to kind of have that process set up and kind of, you know, well understood and functioning before we kind of, you know, get to that. So, it’s definitely being done in parallel, but yeah, it looks like an interesting one as well.

00:30:41 – 00:30:47 – Rachael Eynon

Great. Yep, and that closes, in about a month, is that right?

00:30:48 – 00:30:49 – Alex Ikonic

Yes. Yes, a bit of tight one that one.

00:30:50 – 00:31:03 – Rachael Eynon

Yes. Great, so yeah, plenty for everyone to be digesting and responding to over the next few months, and yeah, lots more on the way on transforming the connections process and data over the next couple of years.

00:31:04 – 00:31:06 – Alex Ikonic

Yeah, definitely a busy time.

00:31:07 – 00:31:12 – Rachael Eynon

Okay. Thanks Alex and thanks everyone for listening and watching.

00:31:13 – 00:31:14 – Alex Ikonic

Thanks, Rachael.

00:31:14 – 00:31:15 – Rachael Eynon

Hope you’ll join us again soon, thanks.

00:31:15 – 00:31:16 – Alex Ikonic

Thanks.