50MW gas genset and 25MW battery storage scheme in Nottinghamshire

2020-02-26T16:30:19+00:00March 16th, 2018|Case Study, Farms & Estates, Grid Connection Services|

Roadnight Taylor secured 50MW export capacity for a gas genset scheme and 25MW import capacity for battery storage and reduced the connection charge by £1.5 million for a landed estate in Nottinghamshire.

40MW gas genset and 10MW battery storage scheme in Shropshire

2020-02-26T16:43:51+00:00March 10th, 2018|Case Study, Commercial & Industrial, Grid Connection Services|

Roadnight Taylor secured 40MW of export capacity and 10MW of import capacity for battery storage behind the same connection for an industrial client in Shropshire.

20MW battery storage scheme in Greater Manchester

2020-02-26T16:50:36+00:00February 12th, 2018|Case Study, Commercial & Industrial, Feasibility Studies, Grid Connection Services|

We secured 20MW of battery storage capacity on our client's redundant urban site and also secured the highest ground rent from a developer we have seen to date.

200kW behind-the-meter solar and battery storage advice in Oxfordshire

2019-11-06T17:05:32+00:00January 8th, 2018|Case Study, Farms & Estates|

We are advising a large stately home on behind-the-meter solar and battery storage. Having secured 200KW of solar and storage capacity, we are now working with independent experts in the renewable heat market to get our clients maximum value from their energy opportunities.

800kW behind-the-meter solar and battery storage advice in Yorkshire

2020-02-26T17:51:10+00:00October 23rd, 2017|Case Study, Commercial & Industrial, Farms & Estates|

Read how we secured grid capacity for 800kW of behind-the-meter battery storage for our Yorkshire clients and the consultancy we are now providing.